Question: Wilton Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. Williston Technologies has gathered the following information
Wilton Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. Williston Technologies has gathered the following information to work with:
Bill of Materials:
Current Inventory Records:
Inventory
Leadtime Currently
Part (in weeks) Lotsize On-hand
A 1 Lot-for-Lot 50
B 1 75 85
C 2 30 100
D 2 50 415
Master Production Schedule:
-Weeks-
Part 1 2 3 4 5 6 7 8 9
A 0 50 100 100 250 0 200 0 50
Please use MRP methodology to develop a materials requirement plan for Williston Technologies.
Which of the following is true about your plan?
I. In Week 9, ending inventory of Part A will be 0.
II. In Week 4, ending inventory of Part B will be 50.
III. The Week 2 Planned Order Releases for Part C is 250.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts