Question: With a _ _ _ _ _ contract, the buyer pays the supplier for allowable performance costs plus a fixed fee payment usually based on

With a _____ contract, the buyer pays the supplier for allowable performance costs plus a fixed fee payment usually based on a percentage of estimated costs.
a.
CPFF
b.
FPIF
c.
CPAF
d.
CPIF