Question: With activities (A through G ) and their expected times (in days) given by the nodes/circles in the following project diagram, the critical path for


With activities (A through G ) and their expected times (in days) given by the nodes/circles in the following project diagram, the critical path for this project is: ABGEFG None of the above AEFGACDG What is the expected completion time for the project in Question 15? 9 days 12 days 28 days 10 days 15 days In order to reduce/crash the completion time of the project in Question 15 by one day, assuming each activity listed below can be feasibly crashed by one day, which of the following should you do? Crash F by one day at a cost of $300 Crash E by one day at a cost of $500. Crash B by one day at a cost of $225. Crash G by one day at a cost of $440. Crash D by one day at a cost of $300