Question: With assistance from the team, the Project Manager has just determined what will be done as a result of uncertain events happening on the project

With assistance from the team, the Project Manager has just determined what will be done as a result of uncertain events happening on the project as well as who will be responsible for monitoring and responding if the events do occur. Which of the following best describes what they have just completed?

Identifying Risk

Planning Risk Response

Planning Secondary Response

Qualitative Analysis