Question: With pure contracts, allowable costs are shared between the parties on a predetermined percentage basis. Select one: Time and materials Cost - sharing Cost pius

With pure contracts, allowable costs are shared between the parties on a predetermined percentage basis.
Select one:
Time and materials
Cost-sharing
Cost pius incentive fee
Fixed-price with incentives
 With pure contracts, allowable costs are shared between the parties on