Question: With regards to the Project Management Maturity Model, what level is the following characteristic: Project audits tend to be performed only when a project fails.
With regards to the Project Management Maturity Model, what level is the following characteristic: Project audits tend to be performed only when a project fails. Multiple choice question. Level 1 Level 2 Level 3 Level 4 Level 5