Question: With respect to PERT and CPM , slack Part 2 A . marks the start or completion of a task. B . is the latest
With respect to PERT and CPM slack
Part
A
marks the start or completion of a task.
B
is the latest time an activity can be started without delaying the entire project.
C
is the amount of time a task may be delayed without changing the overall project completion time.
D
is a task or subproject that must be completed.