Question: With the following data for a 60% capacity, prepare a budget for production at 80% and 100% activity. Production at 60% activity 600 units

With the following data for a 60% capacity, prepare a budget for production at 80% and 100% activity. Production at 60% activity 600 units materials Rs. 100 per unit (100% variable) Materials Rs. 40 per unit (100% variable) Labours Rs. 40 per unit (100% variable) Direct Expenses Rs. 10 per unit (Rs. 6 per unit fixed) Factory expenses Rs. 40,000 (40% fixed) Administrative expenses Rs. 30,000 (60% fixed)
Step by Step Solution
3.36 Rating (159 Votes )
There are 3 Steps involved in it
I Total capacity 600 units 60 1000 units Units at 80 capacity 1000 units x 80 800 units Particul... View full answer