Question: With the network diagram please explain how you made the diagram as I am very confused on how to make it. Thank you. IYou have
IYou have been contracted to undertake a project for a firm. The project parameters are listed in the table below a) Draw a network diagram and determine the critical path for the project. What is the expected completion time (state it explicitly)? b) The client asks you to shorten the project by 3 weeks and will pay you a bonus of $1,200. Is this worthwhile? When you finish crashing 3 weeks from the project, which path or paths are critical