Question: with their tine estimates: i ) Draw the project network. Use activity on node ( A - O - N ) nethod - ( IM

with their tine estimates:
i) Draw the project network. Use activity on node (A-O-N) nethod -(IM)
ii) Identify the critical path. Calculate the length and variance of the critical path. (IM)
iii) Identify the non-critical achivityes. Workout the total slack (TS) and Free slack (FS) for all the noncritical activities. (IM)
iv) state whether the nefwork is sensitive or Insensitive (im)
v) What is the approxirate probability that jobs on the critical path will be completed by the due date of (a)25 ddys,(b)30 days? (6M)
(1)
DATE OF EXAM :-
 with their tine estimates: i) Draw the project network. Use activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!