Question: With your team you are working on a project that is supposed to be completed in FOUR months. You planned that EACH MONTH you are

With your team you are working on a project that is supposed to be completed in FOUR months. You planned that EACH MONTH you are going to spend $15000 on the work for the month.

At the end of the FIRST month you have spent the expected amount of $15000, but you have completed only two thirds (2/3) of the work.

Answer the following questions: a) What is the Earned Value at the end of the first month. b) Calculate the Cost Variance and the Schedule Variance c) Calculate the Cost Performance Index and the Schedule Performance Index d) Analyze the progress of the project. Is the project behind or on schedule? Is the project above budget? e) Calculate the Estimate At Completion f) Calculate how long time will take for the project to be completed.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!