Question: without BAC how to solve the problem? i cant find out the solution Your current project is running with the following indicators: - CPI =
without BAC how to solve the problem? i cant find out the solution

Your current project is running with the following indicators: - CPI = 1.07 - SPI = 1.1 - AC = $22,500 You are 4 weeks into a 12-week project, and some of the financial data is missing (the previous project manager left the project unexpectedly). Spending will continue at the budgeted rate - no BAC variance. Given the information above, compute: - EV - PV - BAC - EAC - ETC VAC - TCPI for BAC PRO RA