Question: wo alternatives, code - named X and Y , are under consideration at Guyer Corporation. Costs associated with the alternatives are listed below. Alternative X

wo alternatives, code-named X and Y, are under consideration at Guyer Corporation. Costs associated with the alternatives are listed below.
Alternative X Alternative Y
Materials costs $ 46,000 $ 66,500
Processing costs $ 50,500 $ 50,500
Equipment rental $ 19,000 $ 19,000
Occupancy costs $ 18,000 $ 26,900
What is the financial advantage (disadvantage) of Alternative Y over Alternative X?
Multiple Choice
$(148,200)
$133,500
$162,900
$(29,400)