Question: Work Element Time (Sec) Immediate Predecessor(s) Use the longest work element rule to balance the assembly line described in the following table and Figure 5.16

Work Element Time (Sec) Immediate Predecessor(s)

Work Element Time (Sec) Immediate Predecessor(s) Use the longest work element rule to balance the assembly line described in the following table and Figure 5.16 so that it will produce 40 units per hour. A 40 None B 80 C 30 F H D 25 B B 80 15 45 E 20 40 G F 15 B 75 30 ( 15 G 60 B H 45 D E 20 10 10 EG Figure 5.16 Precedence Diagram J 75 F a. What is the cycle time? b. What is the theoretical minimum number of workstations? c. Which work elements are assigned to each workstation? d. What are the resulting efficiency and balance delay percentages? e. Use the shortest work element rule to balance the assembly line. Do you note any changes in solution? K 15 HIJ Total 415

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!