Question: Work in Process Debit: Direct Materials. $61,000 Direct Labor $104,000 Overhead $187,200 Ending Balance $94,000 Credit: Beginning balance $0 Transferred Out $258,200 Only Job #007
Work in Process
Debit:
Direct Materials. $61,000
Direct Labor $104,000
Overhead $187,200
Ending Balance $94,000
Credit:
Beginning balance $0 Transferred Out $258,200
Only Job #007 was still in process at the end of March and this job been charged with $52,000 in direct materials cost.
The amount of overhead costs applied to do #007 during March was:
$42,000
$15,000
$27,000
$52,000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts