Question: Work involves the activities as shown in the table. Completion of activities C and E is deliverable.A 5 day, 40 hour week, is to be

Work involves the activities as shown in the table. Completion of activities C and E is deliverable.A 5 day, 40 hour week, is to be worked. The project started on Monday 2nd August 2020.

Activity

Predecessors

Duration

(Days)

Workers needed

($50/Hour)

Machines needed

($100/Hour)

Percent completed

after 8 working days

A

10

4

2

77

B

2

15

5

100

C

A

1

10

4

0

D

8

4

0

82

E

A

4

8

2

0

F

A, D

12

8

2

0

G

D

5

7

1

0

H

C, E

10

10

3

0

I

F, G

3

4

0

0

Use MS Project to analyse the project.

a) What is the estimated completion date for the project?

b) What is the estimated date to achieve the deliverable?

c) What is the total estimated cost of workers and machines for the project?

d) What is the estimated cost of workers and machines for the work completed after 8

working days?

e) After smoothing the project within the available slack, what is the minimum number

of workers required to complete the project by the same date?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!