Question: Worker 1 2 3 4 5 6 Task A 10 12 16 B 21 20 20 C 45 46 36 44 D 49 45 32
| Worker | 1 | 2 | 3 | 4 | 5 | 6 |
| Task | ||||||
| A | 10 | 12 | 16 | |||
| B | 21 | 20 | 20 | |||
| C | 45 | 46 | 36 | 44 | ||
| D | 49 | 45 | 32 | 46 | ||
| E | 11 | 12 | 8 | 6 | ||
| F | 24 | 30 | 38 |
For situation 1 given, conduct the same analysis to find assignment of workers so that minimum number of person hours is met but under the relaxed condition that workers can take on no more than 2 tasks and some will have no assignment of tasks on the project. What is the total number of person hours to complete all the tasks based on the lowest value?