Question: Workers in the Bowness Carpentry Shop ( BCS ) work 1 2 - hours shifts to make wooden tables. They take three 1 5 -

Workers in the Bowness Carpentry Shop (BCS) work 12-hours shifts to make wooden tables. They take three 15-minute breaks and one 45-minute lunch break. There are two shifts per day. For the owners to achieve their annual production target, the factory must produce 150 tables per day.
Question 25(2 points)
What will be the net available time in minutes per day?
Question 25 options:
1260
1206
1276
1266
Question 26(2 points)
Calculate the takt time in minutes.
Question 26 options:
8.40
8.04
0.84
18.40
Question 27(2 points)
With process improvement, the BCS started producing 175 tables per day. What will be the new takt time in minutes?
Question 27 options:
7.2
17.5
27.2
0.72

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!