Question: Workers /Machine 1 2 3 4 5 6 1 65 50 60 55 80 0 2 30 75 125 50 40 0 3 75 35
| Workers /Machine | 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | 65 | 50 | 60 | 55 | 80 | 0 |
| 2 | 30 | 75 | 125 | 50 | 40 | 0 |
| 3 | 75 | 35 | 85 | 95 | 45 | 0 |
| 4 | 60 | 40 | 115 | 130 | 110 | 0 |
| 5 | 90 | 85 | 40 | 80 | 95 | 0 |
| 6 | 145 | 60 | 55 | 45 | 85 | 0 |
1.Solve this problem using Johnson Rule
2.Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using FCFS, SPT, EDD, in which priority rule should the jobs be processed? All dates are specified as days from today.
| Job | Processing Time (days) | Job due date (days) |
| A | 4 | 7 |
| B | 2 | 4 |
| C | 8 | 11 |
| D | 3 | 5 |
| E | 5 | 11 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
