Question: write a report 1 . Introduction / System Description: The Family Planning Research Center of Nigeria, led by Dr . Adinombe Watage, is undertaking a
write a report IntroductionSystem Description:
The Family Planning Research Center of Nigeria, led by Dr Adinombe Watage, is undertaking a critical project to demonstrate the acceptance of a new birth control method. This involves organizing and training field teams for educational and outreach activities. The system encompasses various activities, logistical arrangements, and training components, as outlined in TABLE
Problem Statement:
The key challenge facing the Family Planning Research Center is the ambitious goal of completing the project within a tight day timeframe. The initial assessment by the chief clerk, Louis Odaga, revealed that the calculated time requirements sum up to days, posing a significant obstacle to project completion. The personnel constraint of only individuals adds another layer of complexity.
Project Objectives:
The overarching objectives of the project include successfully organizing and training field teams, demonstrating the acceptance of the new birth control method through effective educational and outreach activities, and overcoming time and personnel constraints to ensure timely project completion.
Scope of the Project:
The project's scope encompasses a comprehensive approach to organizing and training field teams, material preparation, and logistical arrangements. It involves understanding the critical path and evaluating options for project completion within the specified personnel limitations
Contribution of the Project:
This project aims to contribute significantly to the successful implementation of a new birth control method by ensuring efficient training and outreach activities. Additionally, it addresses the challenge of completing the project within the specified timeframe and under personnel constraints, making it a crucial endeavor for the Family Planning Research Center.
Methodology:
Data Collection: The project activities, their dependencies, and the respective time and staffing requirements were identified during a meeting with the office staff. This data formed the foundation for subsequent analyses.
Data Analysis Technique:
A network diagram was constructed to visualize task dependencies and identify the critical path. Utilizing cost and time data from TABLE the critical path activities were analyzed to determine the most efficient schedule.
Data Analysis and Results:
The network diagram revealed the critical path to be AECIJK with a total duration of days. However, considering the personnel constraint of individuals, the current schedule cannot be achieved.
Interpretation of the Analysis:
The personnel constraint emerges as a significant challenge, rendering the current schedule unattainable. To expedite the schedule, the recommendation is to crash activities, particularly those on the critical path. This entails additional costs that Dr Watage must carefully evaluate against the urgency of project completion.
Discussion on Improvements or Modifications to the System:
To achieve the day schedule, the recommendation is to crash activities C J and K incurring a total cost of $ Dr Watage must weigh the urgency of project completion against the financial implications and seek approval from the Pathminder Foundation.
Conclusion:
In conclusion, the project faces substantial challenges in terms of time constraints and limited personnel availability. The recommended crashing activities provide a viable solution, but careful consideration of costs and benefits is necessary. Dr Watage is urged to assess the urgency of project completion against the financial implications and seek necessary approvals.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock