Question: write probability and impact matrix for this Risk ID Risk Description Probability (1-5) Impact (1-5) Risk Score (P x I) Priority 1 Design Changes 3
write probability and impact matrix for this
Risk ID | Risk Description | Probability (1-5) | Impact (1-5) | Risk Score (P x I) | Priority |
1 | Design Changes | 3 | 4 | 12 | High |
2 | Delays in Regulatory Compliance | 3 | 4 | 12 | High |
3 | Safety Hazards | 3 | 4 | 12 | High |
4 | Cost Overruns | 4 | 5 | 20 | Critical |
5 | Weather-related Delays | 4 | 4 | 16 | High |
6 | Expansion of Hospital Services (Opportunity) | 3 | 4 | 12 | High |
7 | Contractor Performance Issues | 3 | 4 | 12 | High |
8 | Inspection Failures | 4 | 4 | 16 | High |