Question: write the answer in 2-3 steps with clear hand writing or typed answer A machine center in a job shop for a local fabrication company
write the answer in 2-3 steps with clear hand writing or typed answer

A machine center in a job shop for a local fabrication company has five unprocessed jobs remaining at a particular point in time. The jobs are labeled A, B, C, D, and E in the order that they entered the shop. The respective processing times and due dates are given in the table below. What is the sequence the of jobs by CR rules? Job B Processing Time 10 2 11 31 3 Due Date 32 55 34 60 35 mio