Question: X 1 3 - 1 ( Algo ) In month 9 the following... In month 9 the following project information is available: Actual cost is

X13-1(Algo) In month 9 the following...
In month 9 the following project information is available:
Actual cost is $1,900
Earned value is $1,800
Planned cost is $2,100.
Compute the CV and SV for the project.