Question: X Company uses an activity-based costing overhead allocation system. It has identified three activities and three cost drivers. The activities and budgeted costs are as
X Company uses an activity-based costing overhead allocation system. It has identified three activities and three cost drivers. The activities and budgeted costs are as follows:
| Activity | Budgeted Cost | |
| Setup | $112,000 | |
| Purchasing | $58,000 | |
| Machine Maintenance | $55,000 | |
The following cost driver information is available for the company's only two products, A and B:
| Cost Driver | Product A | Product B |
| setup hours | 32,100 | 76,600 |
| purchase orders | 51,000 | 40,100 |
| machine hours | 69,900 | 50,600 |
How much overhead was allocated to Product A? (round overhead rates to two decimal places)?