Question: X Company's 2015 budgeted cost function for variable overhead was C=$8.50X and its budgeted cost function for fixed overhead was C=$237,800.The following information is also
X Company's 2015 budgeted cost function for variable overhead was C=$8.50X and its budgeted cost function for fixed overhead was C=$237,800.The following information is also available for 2015:
| Master | Actual | |
| Budget | Results | |
| Production | 10,300 units | 11,800 units |
| Total variable costs | $87,550 | $103,057 |
| Total fixed costs | $237,800 | $238,638 |
1. What was the total overhead flexible budget variance for 2015 [submit a favorable variance as a positive number and an unfavorable variance as a negative number]?
2. What was the total overhead static budget for 2015?