Question: X Company's 2018 budgeted overhead cost function was C=$11.30X + $196,100, where X is the number of units produced. The following information is also available
X Company's 2018 budgeted overhead cost function was C=$11.30X + $196,100, where X is the number of units produced. The following information is also available for 2018:
| Master Budget | Actual Results | |
| Production | 10,300 units | 13,700 units |
| Total variable costs | $116,390 | $183,369 |
| Total fixed costs | $196,100 | $199,616 |
1. What was the total overhead static budget for 2018? 2. What was the total overhead flexible budget variance for 2018 [a positive number means a favorable variance and a negative number means an unfavorable variance]?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock