Question: X U + D Question 27 Job 450 requires $9,800 of direct materials, $6,400 of direct labor, 590 direct labor hours, and 400 machine hours.

 X U + D Question 27 Job 450 requires $9,800 of

X U + D Question 27 Job 450 requires $9,800 of direct materials, $6,400 of direct labor, 590 direct labor hours, and 400 machine hours. Manufacturing overhead is computed at $14 per direct labor hour used and $10 per machine hour used. The total cost of Job 450 is O $28,460. O $16,200. O $24,460. O $12,260