Question: x=4,y=6,d=50 With Explanation please Need Help A 5 min D 4 min C X min F Y min B 3 min E 1 min Answer
x=4,y=6,d=50
With Explanation please
Need Help
A 5 min D 4 min C X min F Y min B 3 min E 1 min Answer the following questions: 1 1. How long does it take to produce one product? (1 pts) 2. Assuming that the company works 8 hours a day, and the daily demand is D products, what is the cycle time? (2 pts) 3. Theoretically, what is the minimum number of stations required? (1 pts) 4. Balance the assembly line by dividing the process into workstations? (2 pts) 5. What is the efficiency of this system? (1 pts) Be careful! This is NOT a capacity