Question: XC What is the critical path(s) and the completion time for this project? D6 B 10 A 5 G4 E6 C8 F8 Paths A-B-D-G and

XC What is the critical path(s) and the
XC What is the critical path(s) and the completion time for this project? D6 B 10 A 5 G4 E6 C8 F8 Paths A-B-D-G and A-C-F-G, 25 days Path A-B-D-G, 25 days Path A-C-E-G, 23 days Path A-C-F-G, 25 days None of the these