Question: Xcellenta Systems is a local software development firm that is currently evaluating six different potential projects. There are not sufficient resources to take on all

Xcellenta Systems is a local software development firm that is currently evaluating six different
potential projects. There are not sufficient resources to take on all of these, but more than one
will be selected. A 0-1 integer programming model is planned to help determine which of the
six opportunities to choose, and variables X1, X2, X3, X4, X5, and X6 are being used to represent
the six choices. For each of the following situations, please write a constraint (or several
constraints) that would accomplish the stated restriction:
(a) At least 3 of these choices are to be selected
(b) Either project 1 or project 4 must be undertaken, but not both
(c) If project 4 is selected, then project 6 must also be selected. However, if project 4 is
not selected, it is still possible to select project 6.
(d) Project 5 cannot be selected unless both projects 2 and 3 are also selected.
(e) Project 5 must be selected if both projects 2 and 3 are also selected.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!