Question: XY Inc. provides the following data for June 2011 when 13,000 Units are manufactured: Standard Material Cost (Per Unit) 6.20 kg @ $ 10.25/kg Actual

XY Inc. provides the following data for June 2011 when 13,000 Units are manufactured:

Standard Material Cost (Per Unit) 6.20 kg @ $ 10.25/kg

Actual Material Cost (Per Unit) 6.85 kg @ $ 13.8/kg

Standard Labor cost (Per Unit) 5.5 hrs @ $ 14/hr

Actual Labor cost (Per Unit) 5.30 hrs @ $ 15.2 /hr

a) Calculate:

Direct Material Price Variance

Direct Material Quantity/Usage Variance Total Material Cost Variance

Direct Labor Rate Variance Direct Labor Efficiency Variance Total Labor Cost Variance

(b): Calculate Variable Overhead Spending Variance if actual labor hours used are 360, standard variable overhead rate is $11.40 per direct labor hour and actual variable overhead rate is $10.30 per direct labor hour. Also specify whether the variance is favorable or unfavorable.

(c): Calculate the variable overhead efficiency variance using the following figures:

Number of Units Produced

720

Standard Direct Labor Hours Per Unit

1.2

Actual Direct Labor Hours Used

360

Standard Variable Overhead Rate

$11.40

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!