- XYZ Company is looking ahead to the last week in next month’s production. Production time for the week will be 40 hours. Job 1 is scheduled for a workstation and is for a lot size of 20 parts. This job requires 2 hours to set the machine up and 75 minutes to run each part. Job 2 is for 10 parts, requires 3 hours to set up, and 30 minutes to run each part. Job 3 is being considered and requires just 1 hour to set up.
- If it takes 15 minutes to make each part for job 3, how many of these parts can XYZ Company make and still meet. Their commitment for parts for job 1 and job 2?
- What would the planned utilization rate be for the first two jobs combined?