Question: XYZ Project has 20 activities, each activity uses 4 different resources with their limits given in the following table. It is required to schedule the

XYZ Project has 20 activities, each activity uses

XYZ Project has 20 activities, each activity uses 4 different resources with their limits given in the following table. It is required to schedule the project so that the daily resource requirements do not exceed the resource limits. Activity Duration . - 6 3 6 H Daily Resource Requirements Predecessors R1 R2 R3 R4 ---- 5 / 2 / 2 / 2 3 A / 2 / 4 4 ---- 5 A, B D4 A,B 5 G, H F 1 CE E, G, H I, K F,L 1 4 L 5 J, M, N 3 0 / 4 5 DO 5 PAR 2 4 0 1 K 3 2 L M N o 2 5 8 2 6 2 - Daily Resource Limits 8 12 12