Question: Year Project X ( RM ) Project Y ( RM ) 0 ( 5 0 , 0 0 0 ) ( 5 0 , 0

Year
Project X (RM)
Project Y (RM)
0
(50,000)
(50,000)
1
15625
0
2
15625
0
3
15625
0
4
15625
0
5
15625
100,000
The companys cost of capital is 10 percent. Calculate and answers to the followings:
(d) Which project would you choose and state your reasons.