Question: yes, this table and the question is complete. please answer asap! The table below provides data on activities for a project. Use this data to

yes, this table and the question is complete. please answer asap!
The table below provides data on activities for a project. Use this data to answer the question below. Activity Duration (weeks) Crashes Available Preceding Activity(ies) (weeks) Crashing Cost/Week 6 2 176 B 3 0 74 4 0 A 70 2 2 AB 87 3 1 C 90 4 1 CD 69 1 2 D 155 U I 2 1 EF 198 1 3 1 G 198 1 0 Question 39 pts How quickly can the project be completed and at what cost? If the project's variable cost is $200 per week, how quickly should the project be completedStep by Step Solution