Question: You and your team are currently developing the project charter and are looking for valuable inputs you can use to complete it. All of the
You and your team are currently developing the project charter and are looking for valuable inputs you can use to complete it. All of the following are inputs in the Develop Project Charter process except?
A: Business case
B: Project management plan
C: Enterprise environmental factors
D: Project statement of work
Explain your answer 150 words