You are a contractor hired to haul solid-waste for the county. You must choose one of two sites.
The costs associated with each site are in the following table:
Cost
Site A
Rent ($/yr)
13,000
Site B
Hauling cost ($/yd3-mi)
45,000
2.30
Average haul distance (mi)
2.30
4
The county will pay you $11.00/yd3. You will haul 30,000 yd3 over the next year.
3
a. What is the total yearly cost for each alternative?
b. What is the total yearly profit for the contractor?
c. Which site should you choose?1-2
You are a contractor hired to haul solid-waste for the county. You must choose one of two sites.
The costs associated with each site are in the following table:
The county will pay you $11.00yd3. You will haul 30,000yd3 over the next year.
a. What is the total yearly cost for each alternative?
b. What is the total yearly profit for the contractor?
c. Which site should you choose?
You are a contractor hired to haul solid - waste

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!