Question: You are a PM on effort to develop a new software feature.The plan is broken down into tasksperbelow. Eachphasestarts whentheprior onefinishes.Todayistheendofmonth 5 and is noted

You are a PM on effort to develop a new software feature.The plan is broken down into tasksperbelow. Eachphasestarts whentheprior onefinishes.Todayistheendofmonth 5 and is noted in the Status column.

Task

Duration

Budget

Status-endofmonth 5

Requirements

1month

$10,000

Complete,spent$10,000

Architecture

1month

$10,000

Complete, spent$12,000

Design

1month

$10,000

Complete,spent$12,500

Code

2months

$20,000

25%complete,spent $7,000

Test

1month

$10,000

Not started

Assumeworkwillcontinue atcurrentrate.Completebelow.

Formula

Calculation

Result

PV

EV

AC

BAC

CV

CPI

SV

SPI

EAC

ETC

VAC

TCPI

Status

QuizQuestion2

SITUATION:

TheACMEcompanyisdrillingapipelineunderneathariver.Itrequiresacomplexboring machine with which they have little experience

Iftheydon'toperate theboringmachine properly,theycoulddamagethemachineand/or riverbank.If they damage the riverbank, environmental groups will work to prevent them from getting future permits for similar projects.

Damagingtheboringmachine couldcost$50,000-$250,000inrepairsand2-4weeksinlost time.

PROBABILITIES:

Theseweredeterminedfromtheexperiencewithinthecompany andinterviewswith2 other companies using the boring machine

ITEM

PROBABILITY

$75,000Equipment Damage

20%

$200,000EquipmentDamage

20%

NoEquipmentDamage

60%

RiverbankDamage

20%

What'stheprobablecostofequipment damage?Explainyouranswer.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!