Question: You are a program manager for your organization. Your program will include seventeen projects over the life of the program. You may create a component

You are a program manager for your organization. Your program will include seventeen projects over the life of the program. You may create a component project at any time in a program EXCEPT during what time of the program?
SELECT THE CORRECT ANSWER
Initiating
Closing
Monitoring and controlling
Planning