Question: You are a project manager constructing six additional offices in a building. Each of the six offices is identical; the project cost is estimated to

You are a project manager constructing six additional offices in a building. Each of the six offices is identical; the project cost is estimated to be $300,000. Construction is expected to take 5 weeks.

You are creating a report for your sponsor at the end of week 2 when two rooms are complete. Work has not begun on room number 3 is yet.

So far you have spent $118,000 and the expectation is that project expenses will continue at this rate of for the project duration.

Calculate these Earned Value Metrics

  1. Budget at completion (BAC): How much will my project cost?
  2. Planned value (PV): What're our planned value at a point in time?
  3. EV? (Earned Value)
  4. AC? (Actual Cost)
  5. CV? (Cost variance)
  6. SV? (Schedule Variance)
  7. Cost performance index (CPI): a) What is our CPI? b) How much are we earning for each dollar spent?
  8. Schedule performance index (SPI): a) What is our SPI? b) How are we progressing compared to the schedule?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!