You are a project manager for a large project that is due to start in 2022. You have been requested to provide an estimate of the costs of the project within a range of -10% to +25%. Of what is this an example?
a.
Analogous estimate
b.
Rough Order of Magnitude estimate
c.
Definitive estimate
d.
Budgetary estimate