Question: You are a project manager for a major information systems project. Someone from the quality department comes to see you about introducing a quality requirement
You are a project manager for a major information systems project. Someone from the quality department comes to see you about introducing a quality requirement that they failed to mention. This net new requirement will cause the project to exceed its approved budget. What step should NOT be taken? Question 21 options: a) Escalate the proposed change to the director of the quality department b) Document the proposed change c) Determine the impact of the change on the triple constraint d) Seek guidance from designated project stakeholders to implement the proposed change or not e) All of the above