Question: You are a project manager for a medium-sized human resource training centre. You are required to plan for training and development for the company. Based
You are a project manager for a medium-sized human resource training centre. You are required to plan for training and development for the company. Based on Table B scheduling, construct a network for the following training and development project.
Table: Training and Development project scheduling
| Activity | TE (weeks) | Preceding activities | |
| A | Select personnel | 3 | none |
| B | Invite personnel | 5 | none |
| C | Budget ok? | 14 | a |
| D | Prepare materials | 5 | a |
| E | Engage instructor | 4 | b |
| F | Select date | 7 | b |
| G | Remind personnel | 8 | d, e |
| H | Start project | 5 | g, f |
1- Draw the applicable network.
2- Find the critical path.
3- Assume activity A (hire trainers) took 5 weeks. Replan the project.
4- From where would you suggest transferring resources, and to what activities, so that the original target training date may be maintained.