Question: You are a project manager for a medium-sized human resource training centre. You are required to plan for training and development for the company. Based

You are a project manager for a medium-sized human resource training centre. You are required to plan for training and development for the company. Based on Table B scheduling, construct a network for the following training and development project.

Table: Training and Development project scheduling

Activity

TE (weeks)

Preceding activities

A

Select personnel

3

none

B

Invite personnel

5

none

C

Budget ok?

14

a

D

Prepare materials

5

a

E

Engage instructor

4

b

F

Select date

7

b

G

Remind personnel

8

d, e

H

Start project

5

g, f

1- Draw the applicable network.

2- Find the critical path.

3- Assume activity A (hire trainers) took 5 weeks. Replan the project.

4- From where would you suggest transferring resources, and to what activities, so that the original target training date may be maintained.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!