Question: You are a project manager for a new project and have figure out the following dependencies: Activity A can start immediately and has an estimated
You are a project manager for a new project and have figure out the following dependencies:
Activity A can start immediately and has an estimated duration of 3 weeks.
Activity B can start after activity A is completed and has an estimated duration of 3 weeks.
Activity C can start after activity A is completed and has an estimated duration of 6 weeks.
Activity D can start after activity B is completed and has an estimated duration of 8 weeks.
Activity E can start after activity D is completed and after activity C is completed. This activity takes 4 weeks.
Develop the CPM diagram and answer the following questions.
What is the duration of the project?
What is the float of activity B?