Question: You are a project manager for a project that is estimated to be completed in 65 weeks. The direct cost for that schedule is $1,200,000.
You are a project manager for a project that is estimated to be completed in 65 weeks. The direct cost for that schedule is $1,200,000. The indirect costs associated with the project is $5000 per week and penalty costs after week 62 is $10,000 per week. In an effort to reduce the project schedule, you crash the cheapest activity - Activity J - for a maximum of 4 weeks at a cost of $2,000. What is the new project cost?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
