Question: You are a project manager for Victoria Constructions, overseeing the construction of the Perth Commercial Complex in West Perth. The project entails building a multi-story

You are a project manager for "Victoria Constructions," overseeing the construction of the Perth Commercial Complex in West Perth. The project entails building a multi-story commercial structure with offices, retail spaces, and a parking area within 18 months and a $10 million budget. Calculate Planned Value (PV), Earned Value (EV), and Actual Cost (AC) at the end of Month 6, given a $6 million budget, planned completion value of $4.5 million, and actual cost of $5.2 million.