Question: You are a project manager for your organization. Your project is to install several devices for one of your company's clients. The client has requested

You are a project manager for your organization. Your project is to install several devices for one of your company's clients. The client has requested that you complete a few small tasks that are not in the project scope. To maintain the relationship with the client, you oblige her request and complete the work without informing your company. This is an example of which of the following?
A violation of ethics
Contract change control
Integrated change control
Effective expert judgment