Question: You are a project manager on a U . S . $ 5 , 0 0 0 , 0 0 0 software development project. While

You are a project manager on a U.S. $5,000,000 software development project. While working with your project team to develop a network diagram, you notice a series of activities that can be worked on in parallel but must finish in a specific sequence. What type of activity sequencing method is required for these activities?
Critical path method
Just in Time diagram method
Precedence diagramming method
Operational diagramming method