Question: You are a project manager that has been assigned to manage a project of developing new flavour of muffins for the Tim Horton's restaurant chain.
You are a project manager that has been assigned to manage a project of developing new flavour of muffins for the Tim Horton's restaurant chain. Which phase of the project management life cycle should you identify and analyze potential risks?
Execution
Planning
Definition
Closing