Question: You are a project manager working on a project that requires 1 0 0 tables to be built in five weeks with an overall budget
You are a project manager working on a project that requires tables to be built in five weeks with an overall budget of $ You have just begun week three. To date, you have spent $ with tables successfully built. Assuming that the production schedule and budget are evenly spread over the project duration, what is the status of the project?
a The project is progressing at of the expected rate
b The project is one week ahead of schedule
c The project is $ under budget.
d The project is on budget.