Question: You are a project manager working on a project that requires 1 0 0 tables to be built in five weeks with an overall budget

You are a project manager working on a project that requires 100 tables to be built in five weeks with an overall budget of $10,000. You have just begun week three. To date, you have spent $2,000 with 40 tables successfully built. Assuming that the production schedule and budget are evenly spread over the project duration, what is the status of the project?
a) The project is progressing at 200% of the expected rate
b) The project is one week ahead of schedule
c) The project is $2000 under budget.
d) The project is on budget.
 You are a project manager working on a project that requires

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!